Keystone Pursuit
Keystone Pursuit

Draws — Pay Application

AIA G702 / G703 · Draw 4 · I-65 Retail Pad (Messer)

AI-assisted
Contract sum
$1.5M
18 SoV lines
Completed to date
77%
$1.2M incl. stored
Current payment due
$340.4K
Draw 4
Retainage held
$117.7K
10% of earned

Application for Payment — G702

Period 4 · certified this application

Total completed & stored to date· 77% of contract$1.2M
Less retainage (10%)($117.7K)
Total earned less retainage$1.1M
Less previous certificates($718.8K)
Current payment due$340,384
Balance to finish (incl. retainage)$476.7K

Draw history

Certified payment per draw · retainage held (running)

$718.8K prior

Schedule of Values — G703

Drag % complete per line to re-certify the draw live · sourced from the takeoff & CPM progress

#DescriptionScheduled value% completeWork completedMaterials storedCompleted & storedBalance to finishRetainage
Earthwork94%$392.2K$26.3K$39.2K
1.1Strip & stockpile topsoil$42.3K
93%
$39.3K$39.3K$3K$3.9K
1.2Mass excavation / cut$225.9K
97%
$219.1K$219.1K$6.8K$21.9K
1.3Structural fill & compaction$117.1K
89%
$104.2K$104.2K$12.9K$10.4K
1.4Fine grade building pad$33.2K
89%
$29.5K$29.5K$3.7K$3K
Storm99%$186.7K$2.7K$18.7K
2.115" RCP storm pipe$116.2K
100%
$116.2K$116.2K$0$11.6K
2.2Area drain / catch basin$53.9K
96%
$51.7K$51.7K$2.2K$5.2K
2.3Detention pond grading$19.3K
97%
$18.7K$18.7K$579$1.9K
Sanitary97%$82.8K$3K$8.3K
3.18" PVC sanitary main$54.9K
98%
$53.8K$53.8K$1.1K$5.4K
3.2Sanitary manhole$30.9K
94%
$29K$29K$1.9K$2.9K
Water97%$186.6K$4.9K$18.7K
4.18" DIP water main$109.6K
97%
$106.3K$106.3K$3.3K$10.6K
4.2Fire hydrant assembly$54.8K
100%
$54.8K$54.8K$0$5.5K
4.3Gate valve & box$27.1K
94%
$25.5K$25.5K$1.6K$2.5K
Paving52%$214K$198.8K$21.4K
5.1Aggregate base course$132.7K
51%
$49.1K$18.2K$67.3K$65.4K$6.7K
5.2Asphalt binder + surface$266.4K
52%
$106.6K$33.1K$139.7K$126.7K$14K
5.3Pavement striping & signage$13.7K
51%
$5.3K$1.7K$7K$6.7K$704
Concrete48%$114.5K$123.4K$11.5K
6.1Curb & gutter$79.7K
48%
$32.7K$5.3K$38K$41.7K$3.8K
6.2Sidewalk / flatwork$133.3K
48%
$54.7K$9.2K$63.9K$69.4K$6.4K
6.3Dumpster pad & approach$24.9K
51%
$9.7K$3K$12.7K$12.2K$1.3K
Contract total$1.5M77%$1.1M$70.5K$1.2M$359K$117.7K