Interactive plan markup · I-65 Retail Pad (Brasfield & Gorrie)

AI-assisted
Estimate total
$1.2M
Approved items
18/18
Avg confidence
85%
approved lines
Divisions
6

Plan sheet C-300 — markup

Grading & utility plan · 1px = 0.5 ft scale

125'-0"storm main
Click start point, then end point
Building footprintUtilitiesPaving / parkingYour markup
Measurements
0 LF0 SF0 count
No measurements yet. Use Distance, Area or Count to mark up the plan.

Line items by division

Toggle Approve to include a line in the estimate

Strip & stockpile topsoil
6,970 CY × $8.76
75%$61.1K
Mass excavation / cut
10,760 CY × $6.44
80%$69.3K
Structural fill & compaction
4,830 CY × $11.68
76%$56.4K
Fine grade building pad
44,680 SF × $0.43
84%$19.2K
15" RCP storm pipe
1,510 LF × $65.46
93%$98.8K
Area drain / catch basin
13 EA × $2,923.25
87%$38K
Detention pond grading
3,370 CY × $13.32
83%$44.9K
8" PVC sanitary main
990 LF × $68.65
88%$68K
Sanitary manhole
5 EA × $7,585.47
80%$37.9K
8" DIP water main
1,260 LF × $62.60
77%$78.9K
Fire hydrant assembly
6 EA × $5,489.21
86%$32.9K
Gate valve & box
7 EA × $2,233.90
87%$15.6K
Aggregate base course
4,060 TON × $29.99
94%$121.8K
Asphalt binder + surface
2,010 TON × $115.79
96%$232.7K
Pavement striping & signage
21,470 SF × $0.42
78%$9K
Curb & gutter
4,750 LF × $31.47
84%$149.5K
Sidewalk / flatwork
10,510 SF × $7.28
86%$76.5K
Dumpster pad & approach
2 EA × $9,126.91
89%$18.3K